
|
LECTURE

*
Model of the project site
A Technical Presentation on 5 March 1998
Speakers: Paul Simon - Project Manager, B&NES;
Miriam Fitzpatrick - Nicholas Grimshaw, Project Architects;
Peter Carey- Donald Insoll, Conservation Architects;
Tim Hamilton- Ove Arup, Project Engineers
The BRLSI meeting room was full to hear Paul Simon and the Design
Team give a technical presentation on how the ideas for this successful
Millennium Project were formulated and how the design work for the project
was progressing.
In his introduction, Victor Suchar reminded the audience that in May
1996 after the first Millennium bid (which had included other features
besides the Spa) had failed, the participants in a meeting at the Institution
chaired by Don Foster MP, had unanimously urged the several councillors
and officers present to relaunch the bid for the Spa Project only. It
was therefore most appropriate for Paul Simon to return to the Institution
to give a report on the work in progress.
Paul Simon assured those present that the commitment and the resources
for the Spa Project continued and that the scheme was on schedule for
opening in the year 2000.
Miriam Fitzpatrick explained how the design team want to enliven the
area where the Spa was located and to draw people into the Spa complex.
Lighting and resurfacing were two important tools in their plans. Through
a variety of slides, she showed how the spa water would be available
on a variety of levels leading to a roof-top pool at a height which
linked it to the green hills surrounding Bath.
Peter Carey revealed how the Baths in the Spa Project area had developed
over time from 1775 when the Council first approached John Wood the
Younger to build the Hot Bath. The cube dimension featured in the Millennium
Spa Scheme is similar to that of the John Wood design.
Energy conservation is an important element in the complex. Tim Hamilton
explained how a comfortable environment for bathing would be achieved
with the minimum possible use of energy. Another objective is to use
the water in as natural a state as possible, although some filtering
and disinfection will be necessary. Paul Simon concluded the meeting
by saying how pleased he was that public opinion overwhelmingly supported
the modern design.
Questions from the audience included asking about other water features;
an arts application concerned with this is in process. Others wondered
how much of the water would be used. Two springs are involved, which
may leave some surplus for future expansion. Others questioned how many
years of life the Spa would have. lf the Spa is successful, addition
facilities would be required as the projected capacity is limited. Given
the quantity of compounds in the water, it was asked how the project
could ensure that the pipes were kept clear. The audience was assured
that this matter was getting serious attention. As to the price for
using the facilities, it was stated that a fee of £6 or £7
was projected. Bath residents would have some concessions including
an expected £2 charge for the Cross Bath. Taxpayers have been protected
in the contract negotiated with the Operators through a variety of maintenance
requirements.
This was a highly informative presentation, and the Project Team has
been invited to make a full presentation of the final design on 13 May.
Betty Suchar
BATH SPA FINAL DESIGN
A Presentation on 23 September 1998
Speakers: Nicholas Grimshaw and the Design Team
The Institution was the host to over 200 people who occupied two floors
to hear Nicholas Grimshaw and the Bath Spa Project Team describe the
final design for the New Spa.
Computer-generated pictures showed how the Millennium Spa Buildings
will be
constructed. The spa complex consists of six buildings centred around
the Cross and Hot Baths. The Beau Street swimming pool will be replaced
with the only new building in the complex which will form the core of
the
facility. The contemporary glass and stone design for this building
received widespread support.
The Hot Bath will house individual treatment rooms and the Cross Bath
will
be restored as a working spa primarily for B&NES citizens. On the
Beau Street site, changing rooms, saunas, steam rooms and a plunge pool
will be contained in a three-storey free-standing cube with walls clad
in Bath
stone.
The audience was very interested in the water treatment and other plant
which will be housed in a new basement on the Beau Street site connecting
to existing services in the cellars of Bath Street.
Members of the design team highlighted the fact that the building will
act as a show-case for the latest sustainable technology using the on-site
natural thermal springs as a source of renewable energy. Under-floor
heating will be the source of heat and heat exchangers will convert
residual energy to ventilate the building.
Paul Simon reported that the demolition of the Beau Street building
has begun to allow an archaeological dig to take place. Planning and
listed building applications are scheduled for December 1998; the main
contractors are
expected on site next May, and completion is still targeted for late
2000. He stressed that cost overruns which occur will not fall on the
ratepayers.
As to the cost to the spa user, Mr. Simons estimated that a two-hour
session
would cost £14, a half-day ticket £23 and a full day £32.
B&NES's residents would be entitled to a discount and would be able
to use the Cross Baths for a fee of £3.50.
In closing the meeting, he said it is clear from the large number
attending, that this project has generated a large amount of excitement.
We learned in the following week that in demonstrating substantial resident
support for the spa, this meeting was decisive in convincing B&NES
councillors that the project should be approved.
Victor Suchar
|